: strike on 330 kV substation protection At approximately 15:40, an attack struck the protective structure of transformer equipment at the "Sumy-North" 330 kV substation. No fire or damage to energy infrastructure was recorded. Power supply interruptions did not occur. The hit landed specifically on the Level II physical protection facility built around critical transformers to mitigate drone strikes and shockwaves.